Construction Schedulers
Pinnacle Construction
Timeline view
Add Task
ID
Task
Start
Duration
End
Progress
Assigned
0
Building West
07/01/24
373 d
12/04/25
82%
1
Procurement
07/01/24
218 d
05/16/25
90%
2
Submittal 01xx Steel
07/01/24
108 d
12/01/24
100%
3
Submittal 23xx Skin
12/10/24
90 d
04/15/25
60%
4
Submittal 03xx Finishes
11/28/24
50 d
02/06/25
100%
7
Submittal 30xx Equipment
04/11/24
40 d
06/06/25
0%
8
Make Ready
08/02/24
39 d
09/23/24
100%
9
Utilities
08/02/24
15 d
08/23/24
100%
10
Permitting
08/23/24
19 d
09/19/24
100%
11
Construction Start
08/25/24
0 d
08/25/24
100%
12
Building Foundation / B...
08/23/24
80 d
12/13/24
100%
13
Footings
08/23/24
20 d
09/20/24
100%
14
Shoring
09/20/24
25 d
10/25/24
100%
15
Foundation Walls
10/25/24
22 d
11/26/24
100%
16
Slab On Grade
11/15/24
20 d
12/13/24
100%
17
Core and Sheel
12/02/24
115 d
05/12/25
82%
18
Steel Structure
12/02/24
60 d
02/24/25
60%
19
Decking
01/22/24
26 d
02/27/25
0%
20
Exterior Skin
01/25/24
35 d
03/14/25
0%
21
Exterior Skin
03/12/24
16 d
04/03/25
0%
Jan 2024
Feb 2024
Mar 2024
Apr 2024
May 2024
Jun 2024
Jul 2024
Aug 2024
Sep 2024
Oct 2024
Nov 2024
Dec 2024
Jan 2025
Feb 2025
Mar 2025
Apr 2025
May 2025
Jun 2025
Jul 2025
Aug 2025
Sep 2025
Oct 2025
Nov 2025
Dec 2025
Building West
Procurement
Submittal 01xx Steel
Submittal 23xx Skin
Submittal 03xx Finishes
Submittal 30xx Equipment
Make Ready
Utilities
Permitting
Construction Start
Building Foundation / B...
Footings
Shoring
Foundation Walls
Slab On Grade
Core and Sheel
Steel Structure
Decking
Exterior Skin
Exterior Skin